Customer: Carnival UK

Project: Alfa Laval Ballast Water Treatment System Installation

Project Overview: Complete electrical and mechanical turnkey installation in-service on multiple vessels

Project Highlights:

  • Working in partnership with customers preferred Engineering Solution provider
  • Pre-fabrication of all pipe spools
  • Pre-fabrication of base frames and support frames
  • Installation of new CuNi pipework according to 3D scan survey and installation drawings
  • Installation of Alfa Laval OEM supplied equipment
  • Supply and installation of all interconnecting pipework valves and controls
  • Design, supply and installation of new 690/440V Transformer
  • Design, supply and installation of new 440V Distribution Board
  • LV and control cable installation and termination
  • Full Insulation Resistance Testing of all newly installed cables
Return