Project: MBR Sludge Tanks
Project Overview: Fabricate and install two new stainless steel 316L sludge collection tanks for MBR 1 & 2 and to convert the existing Exhaust Gas Eco. wash tank into a Sludge collection tank for the collection of MBR 3 sludge.
Project Length: 4 months
Project Location: Sailing project onboard a cruise ship
Project Highlights:
MBR Sludge Tank 1
The new Stainless Steel Sludge collection tank shall be fabricated onboard and installed on deck 1 portside between frames 252 – 256 underneath the membrane bioreactor tank No.1 located on deck 2.
- New stainless steel 316L pipework and fittings shall connect to the existing desludge line running from the existing desludge pump on deck 2.
- This pipework shall connect to the newly fabricated stainless steel sludge collection tank.
- The new sludge collection tank shall consist of the below:-
- Screwed Union Sight Glass, 316L SS Base / 304 SS Nut – Viewing Diameter 150mm with wiper and light.
- Sounding line connection.
- Manhole access.
- Gooseneck vent.
- Low level Molbrey Float Switch
- High level Molbrey Float Switch
- The discharge shall run from the tank to the B50 X 50HC Sewage discharge pump.
- It shall then run and connected back into the common overboard discharge line.
MBR Sludge Tank 2
The new Stainless Steel Sludge collection tank shall be fabricated onboard and installed on deck 1 portside between frames 252 – 256 underneath the membrane bioreactor tank No.1 located on deck 2.
- New stainless steel 316L pipework and fittings shall connect to the existing desludge line running from the existing desludge pump on deck 2.
- This pipework shall connect to the newly fabricated stainless steel sludge collection tank.
- The new sludge collection tank shall consist of the below:-
- Screwed Union Sight Glass, 316L SS Base / 304 SS Nut – Viewing Diameter 150mm with wiper and light.
- Sounding line connection.
- Manhole access.
- Gooseneck vent.
- Low level Molbrey Float Switch
- High level Molbrey Float Switch
- The discharge shall run from the tank to the B50 X 50HC Sewage discharge pump.
- It shall then run and connected back into the common overboard discharge line.
MBR Sludge Tank 3
For the collection of the sludge from MBR 3 the redundant exhaust gas eco. wash tank shall be utalised.
- New stainless steel pipework shall branch off the existing common overboard line before the existing automatic valve near frame 96
- The new pipework shall connect into the existing exhaust gas eco. wash tank
- A new screwed Union Sight Glass, 316L SS Base / 304 SS Nut – Viewing Diameter 150mm with wiper and light shall be installed to the tank
- New Low level Molbrey and High level float switches shall be added to the tank
- The pipework shall then run to a new B50 X 50HC Sewage discharge pump and then run back to the common overboard discharge line after the existing automatic valve.
Electrical Scope
MBR Sludge Tank 1:
- Installation of Low level Molbrey Float Switch into new Sludge Tank for MBR 1.
- Installation of High level Molbrey Float Switch into new Sludge Tank for MBR 1.
- Installation of Pump Control Starter Panel for the new Pump for MBR 1.
- Installation of new 25A Circuit Breaker for the supply to the Pump Control Starter Panel.
- Installation of any containment required for supports for cabling.
- Install and terminate 4c 4mm supply cable from Power Board to Pump Control Starter Panel.
- Install and terminate 4c 2.5mm cable from Pump Control Starter Panel to new Pump.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to High Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low ECR.
MBR Sludge Tank 2:
-
- Installation of Low level Molbrey Float Switch into new Sludge Tank for MBR 2.
- Installation of High level Molbrey Float Switch into new Sludge Tank for MBR 2.
- Installation of Pump Control Starter Panel for the new Pump for MBR 2.
- Installation of new 25A Circuit Breaker for the supply to the Pump Control Starter Panel.
- Installation of any containment required for supports for cabling.
- Install and terminate 4c 4mm supply cable from Power Board to Pump Control Starter Panel.
- Install and terminate 4c 2.5mm cable from Pump Control Starter Panel to new Pump.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to High Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low ECR.
MBR Sludge Tank 3:
- Installation of Low level Molbrey Float Switch into new Sludge Tank for MBR 3.
- Installation of High level Molbrey Float Switch into new Sludge Tank for MBR 3.
- Installation of Pump Control Starter Panel for the new Pump for MBR 3.
- Installation of new 25A Circuit Breaker for the supply to the Pump Control Starter Panel.
- Installation of any containment required for supports for cabling.
- Install and terminate 4c 4mm supply cable from Power Board to Pump Control Starter Panel.
- Install and terminate 4c 2.5mm cable from Pump Control Starter Panel to new Pump.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to High Level Float Switch.
- Install and terminate 2x2x0.75mm cable from Pump Control Starter Panel to Low ECR.