Project: PS Shell Insert Plate
Project Overview: Remove existing shell insert place and replace with new.
Project Length: 6 weeks
Project Location: Savannah Yacht Center
Project Highlights:
- Removal of bilge pumps, pipework arrangements and frameworks.
- Remove existing bilge keel & shell plating.
- Form and roll new shell plating.
- Re-weld new shell insert plate.
- Testing requirements;
- 100% NDT – Radiography (RT).
- Vacuum box test.
- Re-installation of bilge pumps, pipework arrangements, frameworks and bilge keel.