Project: Chilled Water Fabrication
Project Overview: Fabrication of Cuni 90/10 copper-nickel pipework, designed to supply sea water to an upgraded chilled water plant
Project Length: Fabrication 6 weeks & Onboard install 2 weeks
Project Location: APM Workshop & MOD Vessel
Project Highlights:
- Workshop fabrication completed as per customer supplied drawings
- Existing Chilled Water Plant decommissioned and removed
- Installation of all fabricate spools, valves and pumps
- NDT/Pressure test completed on site
- Completed in 10 days with a 24 hour working pattern